Enviro Clean Contracted to Handle Millions of Gallons of Storm Water
BARTLESVILLE, Okla., – Enviro Clean has been contracted to oversee all logistics associated with the emptying of existing holding ponds and basins. The basins, which are nearly 100 ft. x 50 ft. in size, and holding ponds currently contain over 1,000,000 gallons of storm water. This project includes very strict conditions (i.e. flow rates, content, etc.) to be maintained throughout the duration of the work. With these conditions in mind, our team has put together a strategic plan that includes removing the storm water, cleaning the basins and containing any potential waste for
disposal. Final steps of the project will include applying waterproofing sealant to both basins.
Enviro Clean plans to complete this work within 6 -7 weeks.